November 5, 2026
The new bridge at Lāniākea is already built, according to a KHON report from mid-October. In July, Goodfellow Bros. reported on its project log that crews had finished grinding and grooving the bridge. Since then, the same log has reported no active work in August, no work scheduled in September, and no work scheduled again in its October 12 update.
Work on the realignment is on hold until a decision is made about seven Native Hawaiian burials found where the new road shoulder and beach parking lot are supposed to go. On the stretch between Haleʻiwa and Waimea, the 2028 finish date depends on that decision, not on concrete.
HDOT's project fact sheet describes the job as moving roughly 1,000 feet of Kamehameha Highway about 90 feet mauka. In a December 2024 update, HDOT placed the work between the Lauhulu Stream Bridge and Pohakuloa Way. That update lists a new two-span bridge over Lauhulu Stream, grading and drainage, new pavement, and upgraded signs, guardrails, street lighting and landscaping. Under the plan, the makai lane of today's highway goes back to a natural state, and the existing mauka lane becomes a shared-use path.
The parking change matters most for daily traffic. As KHON described it in 2024, the project shifts the highway mauka and moves the parking area makai, so pedestrians no longer dart out onto the highway and hold up traffic. Anyone who has inched along that stretch on a winter afternoon knows where the slowdowns start. The project was meant to move the beach crowd and the through traffic apart.
Read month by month, the contractor's log shows a project that was moving well until it stopped.
| Update | What the log reported |
|---|---|
| November 2025 | Riprap work, precast planks in production, bridge deck expected in January |
| January 2026 | Backfill, precast planks, bridge-deck construction |
| February 2026 | Deck forming and rebar, pour planned for month's end |
| March 2026 | Bridge paving in February went well |
| April 2026 | Sleeper slabs, railings, utility beams |
| May 2026 | Approach slabs and end posts |
| July 2026 | Grinding and grooving of the bridge completed |
| August 2026 | No active work, none scheduled |
| September 2026 | No work scheduled for the next two weeks |
| October 2026 | No work scheduled for the next two weeks |
The same page still lists the original substantial-completion milestone of June 2026. Right above it, the revised dates read substantial completion in March 2028 and project completion in May 2028.
In a February 28, 2025 notice, HDOT said no sustained lane closures were planned until the highway tie-in, when traffic moves onto the new alignment. At the time, it expected that step in early 2026. HDOT's Oʻahu roadwork schedule for October 24 to 30 has no Lāniākea realignment entry. It lists only routine tree trimming, pothole filling and sign work around Haleʻiwa.
In KHON's October 16 report, HDOT Director Ed Sniffen named three separate setbacks:
The first two have already cost their time. The third is still unresolved. KHON reported that Sniffen put the total delay at two years past the original end-of-2026 target, with completion now projected for mid-2028. He added that the department did not want to shortcut any of the three issues.
According to minutes in the Oʻahu Island Burial Council's October 14 meeting packet, the seven intact burials turned up while crews were excavating for a cut-off wall between the roadway and the parking lot. The project's engineering representative told the council that the spot is set to become a road shoulder and a parking lot, so both people on foot and vehicles would pass over it.
The location is the heart of the problem. The burials sit inside the part of the project meant to fix the beach-access problem: the makai-side parking that keeps people off the highway. Building the cut-off wall means excavating to its base and then compacting the ground.
Several options were laid out at the council table:
The State Historic Preservation Division's original determination was to preserve the seven burials in place and to relocate the fragmentary remains of one more individual. HDOT then asked SHPD to reconsider, citing concerns about ground compaction. In the council minutes, an SHPD staff member said HDOT had told the agency that compaction would turn the iwi to dust. The staff member had sent HDOT questions about whether the cut-off wall was necessary to the highway.
Diane Fitzsimmons, a former Waialua Moku representative on the council who spoke for the Waialua Civic Club, described the seven as likely members of one family, an infant among them. She told the council:
"This is what we want, we want to preserve in place. However it's going to be to protect them and keep them safe."
According to KHON, community members strongly supported preservation in place at the council's August and September meetings, and Burial Council Chair Makoa Caceres reaffirmed his support for the original determination. The council's draft September 9 minutes also record HDOT's reconsideration request alongside the Civic Club's support for the original ruling.
Each choice has a different effect on the finished project. Preserving the burials in place means engineering a shoulder and parking area around them, or redesigning that corner of the project. Sniffen told KHON that the state wants to "preserve as much as we can in place and work with SHPD to address the rest."
The October 14 packet records no final council decision on the seven burials. On October 16, Sniffen told KHON that the department was working with SHPD and hoped for more clarity by the end of October or in November. He also said, "We're trying not to rush the process."
The next Oʻahu Island Burial Council meeting is scheduled for Wednesday, November 11, 2026, six days after this post goes up. The council's public packets are posted on the SHPD site, and that is where any next step on Lāniākea will show up first in writing.
A decision still leaves the makai side of the project to finish. When construction began in 2024, Sniffen told KHON that work on the makai side would start once the new mauka highway was finished and connected. That work includes resetting parking and turning part of the existing highway into a smaller beach-traffic lane with more landscaping. The contractor's revised dates put substantial completion in March 2028 and full completion in May 2028. Until then, the finished bridge stays in place beside a highway that has not moved.
Life on the North Shore runs on that one stretch of Kamehameha Highway, and projects like Lāniākea shape everyday life here long before they show up on a map. If you want to talk about how the road, the beaches and the slow pace of North Shore projects fit into owning a home in Haleʻiwa, Lex Ferguson is glad to help. Let's Connect.